The company's "Three Phosphorus" special inspection and rectification action has passed the phased acceptance.

2020-01-04


According to the "Yangtze River 'Three Phosphorus' Special Inspection and Rectification Action Implementation Plan" and the "Yangtze River 'Three Phosphorus' Inspection and Rectification Technical Guidelines", the company organized personnel to conduct inspections item by item according to the "Technical Guidelines". Based on the inspection results, rectification measures were formulated and implemented. On January 3, 2020, the project passed the phased acceptance by the expert group. However, some projects will be suspended for installation and rectification starting from January 31, 2020, with plans to complete the remaining rectification projects by the end of March 2020.

Report on the remediation of 'three phosphates'
 
  According to the 'Implementation Plan for the Special Investigation and Remediation of 'Three Phosphates' in the Yangtze River' and the 'Technical Guidelines for the Investigation and Remediation of 'Three Phosphates' in the Yangtze River', the company organized personnel to conduct investigations item by item according to the 'Technical Guidelines'. Based on the investigation results, corrective measures were formulated and implemented. On January 3, 2020, the project passed the phased acceptance by the expert group. However, due to factors such as the large construction volume of some projects, long equipment ordering, manufacturing, supply, and installation cycles, it was difficult to complete the remediation tasks by the end of 2019.
 
On-site inspection
On-site inspection
 
  The company will stop operations for installation and remediation starting January 31, 2020, and plans to complete the remediation by the end of March 2020 (Safety and Environmental Protection Department).

Company, rectification, inspection, 2020, on-site, completion, situation, technology, check

The launch ceremony of the "Beijing University of Chemical Technology - Jianglin Group Flame Retardant Joint Laboratory" was held at Jiangchuan Hotel.

According to the "Yangtze River 'Three Phosphorus' Special Inspection and Rectification Action Implementation Plan" and the "Yangtze River 'Three Phosphorus' Inspection and Rectification Technical Guidelines", the company organized personnel to conduct inspections item by item according to the "Technical Guidelines". Based on the inspection results, rectification measures were formulated and implemented. On January 3, 2020, the project passed the phased acceptance by the expert group. However, some projects will be suspended for installation and rectification starting from January 31, 2020, with plans to complete the remaining rectification projects by the end of March 2020.

2024-11-23

Jianglin Group organized a collective labor public welfare activity

According to the "Yangtze River 'Three Phosphorus' Special Inspection and Rectification Action Implementation Plan" and the "Yangtze River 'Three Phosphorus' Inspection and Rectification Technical Guidelines", the company organized personnel to conduct inspections item by item according to the "Technical Guidelines". Based on the inspection results, rectification measures were formulated and implemented. On January 3, 2020, the project passed the phased acceptance by the expert group. However, some projects will be suspended for installation and rectification starting from January 31, 2020, with plans to complete the remaining rectification projects by the end of March 2020.

2024-11-23

The comprehensive supervision team for the rectification of prominent ecological and environmental issues in yellow phosphorus production enterprises in Yunnan Province visited Jiangphosphorus Group for research.

According to the "Yangtze River 'Three Phosphorus' Special Inspection and Rectification Action Implementation Plan" and the "Yangtze River 'Three Phosphorus' Inspection and Rectification Technical Guidelines", the company organized personnel to conduct inspections item by item according to the "Technical Guidelines". Based on the inspection results, rectification measures were formulated and implemented. On January 3, 2020, the project passed the phased acceptance by the expert group. However, some projects will be suspended for installation and rectification starting from January 31, 2020, with plans to complete the remaining rectification projects by the end of March 2020.

2024-11-23